Akamas National Park: Work Only 17 Percent Complete
The audit office has determined in a special report that work in the Akamas National Forest Park is only 17.67 percent complete despite 94 percent of the contract period having elapsed. The project has a contract value of 6.295 million euros. The report identifies significant deficiencies in the administration and implementation of the work.